The Contract History:

DUNCANS CIVILS CC : CONTRACT CV/ CONTRACT HISTORY

                                                                                                                                                                                                                                                                                                     

Duncans Civils CC is a proud Level 2 BBEEE, QSE Emerging Contractor with an impressive contract history as follow:

                                                                                                                                                                                                                                                                                                             

 NOTES:
 Contract Values indicated:

  1. Labour based contracts –Various contracts are labour based as materials was supplied by the respective Main Contractors ie Concrete, Steel etc.
  2. Other –Supply of all Plant, Labour and Materials.

                                                                                                                                                                                                                                                                                                           

DEVTECH CIVILS (2010) –Izinga Ridge Estate–R285 000.00 (Labour Based).
 Contracts manager –Freddy Vermaak 082 775 0074 .
 Construction of 80 no. Storm water manholes.
 Contract period -3 months.
 Status =Complete.

                                                                                                                                                                                                                                                                                                           

BASIL READ(2011 + 2012) –N12 Boksburg/Benoni –R6 665 639,83 (Labour Based).
 Consultants –SMEC
 Contracts manager –Duanne Maass 082 695 8825 dmaass@basilread.ih.co.za.
 Installation of precast culverts.
 Foundations and footings for median barriers and culverts.
 Installation of Median Barriers +- 3000 units.
 Placing of mass concrete +- 1500 meters.
 Joint sealing +- 10 000 meters between pre-cast barriers.
 Concrete canals and line Drains
 Cast in situ manholes + L3 light masts etc.
 Supply and installation of grouting for median barriers.
 Contract –Part Labour based (Concrete + Steel supplied by Main Contractor).
 Contract period -10 months
 Status =Complete.

                                                                                                                                                                                                                                                                                                       

RAUBEX(2011 + 2012) –N12 Benoni –R3 043 965.38 (Labour Based).
 Contracts manager –Johnny Reid 082 494 4034 Johnny.R@raubex.com.
 Installation of median barriers.
 Supply and installation of grouting for median barriers.
 Placing of mass concrete.
 Joint sealing.
 Line drains.
 Bridge Parapets cast in-situ.
 Contract-Labour based (Concrete + Steel supplied by Main Contractor).
 Contract period =12 months.
 Status complete.

                                                                                                                                                                                                                                                                                                           

GRINAKER LTA (2011)-Medupi Power Station –R142 500.00
 Coring approx. 100 holes to 1,2 meters
 Contract period -1 month
 Status =Complete

                                                                                                                                                                                                                                                                                                   

RMS/ROADMAC SURFACES (2012) –OR Tambo –R5 802 297.90 (ORT 062/2013-2518)
 Consultants –Argus Gibb ( Joao Da Costa)
 Contracts manager –Andre Meissenheimer 082 576 2204 Andre.M@roadmacsurfacing.com.
 Site agent –Jan Van Der Walt 079 504 0669 Jan.V@roadmacsurfacing.com.
 Spall and Joint repairs.
 Reaming and joint sealing –Approx. 40 000 meters
 Construction of pipe culvert.
 Contract period =6 months
 Status =Complete

                                                                                                                                                                                                                                                                                                               

BASIL READ –Golden Highway –R66 012.15
 Contracts manager –Jimmy Strydom 082 449 2929 JStrydom@basilread.ih.co.za.
 Saw cutting of concrete panels.
 Status =Complete.

                                                                                                                                                                                                                                                                                                             

 RAUBEX –R21 Hans Strydom –R65 000.00
 Contracts manager –Hennie Smal 082 771 2031 Hennie .S@raubex.com.
 Repairs to culvert floor + joint sealing.
 Status =Complete.

                                                                                                                                                                                                                                                                                                         

 GROUP 5 (2013 to 2015) - N2 Umdloti to Tongaat +- R 12 500 000,00 (Labour Based)
 Consultants –SMEC (Stuart Anderson).
 Contracts manager –Sean Simmer 071 413 5515.
 Median barrier installations –Line and level complete inclusive of grouting -10 000 meters
 Saw cutting and joint sealing.
 L2 + L3 Butt joints x 20 000meters.
 Supply ,Installation and Epoxy of Dowels & Tie bars +- 40 000 no.
 Concrete repairs –Full depth + Partial depth repairs.
 Status =Complete.

                                                                                                                                                                                                                                                                                                       

 ROADMAC SURFACES/RMS ( 2012/2013)–Kimberley Airport –R2 430 068.20 (KM11/05/AB)
 Ndodana Consultant Engineers (Ross Hess 082 825 3733).
 Contracts Manager –Andre Meissenheimer 082 576 2204 Andre.M@roadmacsurfacing.com.
 Site Agent –Jan Van Der Walt 079 504 0669.
 Joint sealing.
 Concrete and crack and spall repairs.
 Contract period =6 months.
 Status =Complete.

                                                                                                                                                                                                                                                                                                             

MURRAY AND ROBERTS (2013 + 2014)-Transnet City Deep R4 148 607,56
 Contracts manager –Pierre Jansen Van Vuuren 083 646 3004 pierre.vanvuuren@murrob.com.
 Saw cutting of Expansion Joints.
 Reaming and Joint sealing.
 Crack repairs.
 Contract period =18 months.
 Status =Complete

                                                                                                                                                                                                                                                                                                                   

BASIL READ/NEWPORT JV(2013) –Colesberg –R545 315.39
 Site agent –Bradley Abels 083 691 8131 babels@basilread.brsm.co.za.
 Bridge repairs
 Reinforcing steel protection
 Void repairs
 Waterproof coating to soffit and cantilever
 Contract period -3 months.
 Status -Complete.

                                                                                                                                                                                                                                                                                                       

RAUBEX (2013)–Komatipoort –R526 278,80 (Complete)
 Contracts Manager –Theuns Botha 082 462 6816 theuns.b@raubex.com/Louis Steyn.
 Various cast in-situ concrete works.
 Trapesorial Line Drain.
 Contract –Labour based (Materials supplied by main contractor).
 Status -Complete

                                                                                                                                                                                                                                                                                           

LONEROCK(2013) –Nelspruit –R2 476 060.13
 Contracts manager –Alf Kusche 082 498 2156 kusche@lantic.net.
 Site agent –Flip Schoeman 083 300 9318.
 Kerbing and channelling.
 Paving.
 Line drains.
 Contract period -6 Months
 Contract –Labour based.
 Status =Complete.

                                                                                                                                                                                                                                                                                                     

 POWER CONSTRUCTION(2013) –Pretoria (Featherwood Estate) –R5 524 919.96
 Consultants :Aurecon (Jos Keuris 082 829 9149).
 Contracts Manager -Johan Bosman 082 566 7705 jbosman@powergrp.co.za
 Storm water inlet structure.
 Storm water pipes –Installation of storm water pipes, including excavation, placing and bedding.
 Cast In-Situ Manholes and Transition Structures.
 Brickwork –Reinstatement and extension to brick wall.
 Cast in situ canal –Construction of a 750 meter canal x 1200 meters.
 Culvert –Supply and installation of pre-cast culvert units under road level & reinstatement of road.
 Gabions –Supply and install gabion baskets.
 Contract period =7 months.
 Status -Complete

VODACOM(2013)– Vodapark Midrand –R2 318 706.71
 VNA Consultants –Satish Raghubir 082 561 6576.
 Storm water
 Paving
 Kerbing
 Loffelstein Wall
 Status –Complete.

                                                                                                                                                                                                                                                                                               

 ROADMAC SURFACES/RMS & RAUBEX CONSTRUCTION JV –OR Thambo Airport(2013/2014)- R13 917 037.81 (ORT 206/2013)
 Consultants –Aurecon (Hennie Schoeman)
 Contracts manager –Andre Meissenheimer 082 576 2204 Andre.M@roadmacsurfacing.com/Theuns Botha 082 462 6816 theuns.b@raubex.com.
 Joint sealing.
 Crack and spall repairs
 Subsoil drains.
 Cast In-Situ Line Drains.
 Landscaping of Golf Islands.
 Contract period =8 months.
 Status –Complete

                                                                                                                                                                                                                                                                                                       

POWER CONSTRCUTION (2013/2014) –Pretoria (Baviaans Waste Water) –R411 762.72
 Consultants –Worley Parsons
 Contracts manager –Deon Mckinlay 082 469 3531 d.mackinlay@powwrgrp.co.za.
 Joint repairs to waste water structure.
 Installation of BASF Bandage System and various Epoxy repairs.
 Status –Complete.

                                                                                                                                                                                                                                                                                                     

MILLING TECHNIKS(2013) –Durban,Umlazi -R3 321 277,53
 Consultants –SMEC Dawie Joubert
 Site agent –Gerhard Van Der Walt 071 643 3380.
 Concrete repairs, full depth repairs remove and replace defect concrete panels.
 Crack repairs.
 Stitching.
 Join sealing.
 Contract period =2 Months.
 Status –Complete.

                                                                                                                                                                                                                                                                                                 

 AFRISCAN CONSTRCUTION (2013/2014) –Natal ,Middeldrift Reservoir +-R4 800 000.00
 Consultants –ACOM (Lionel Yendall)
 Contracts Manager –Bradley Field 081 494 2597 bradley.field@afriscan.co.za.
 Construction of 940 KL reservoir, excluding earthworks.
 Contract period =6 months.

                                                                                                                                                                                                                                                                                               

 NAMANDLA CIVILS (2013) –PMB International Airport R145 000.00
 Client –ACSA.
 Joint Sealing of Concrete Apron.
 Status =Complete.

                                                                                                                                                                                                                                                                                                   

 ROADMAC SURFACES/RMS (2014)–Vioolsdrift –R396 770,50
 Consultants –Argus Gibb.
 Contracts Manager –Adrian Steele 082 562 1700 Adrian.S@roadmacsurfacing.co.za.
 Site agent –Adriaan Steenkamp 071 485 6444.
 Culvert repairs.
 Status-Complete

                                                                                                                                                                                                                                                                                                     

 ROADMAC SURFACES/RMS (2014) –Colesberg.
 Contract Value R305 023,87.
 Consultants -Aurecon
 Contracts Manager –Wimpie Kogh.
 Site agent –Jan Van Der Walt 079 504 0669 Jan.V@roadmacsurfacing.com.
 Place precast concrete bridge handrails.
 Guardrails.
 Status =Complete.

                                                                                                                                                                                                                                                                                                       

RAUBEX CONSTRUCTION KZN (2014) –Rehabilitation of National Route N11 to N13.
 Contract Value R4 719 466.60.
 Consultant –WSB Consulting Engineers Chris Breytenbach.
 Contracts Manager –Chris Dewing.
 Installation of Subsoil Drainage.
 Installation of Fine Drains.
 Cast In-situ Line Drains.
 Cast In-situ Inlet + Outlet Structures.
 Status –Complete

                                                                                                                                                                                                                                                                                                           

 ESOR CONSTRUCTION (2014/2015) –Nonoti River Bridge.
 Contract Value R3 117 645,39.
 Site Agent - Dean Bosch Cell 072 637 3906
 Construction of River Bridge.
 Concrete repairs to existing structures.
 Gabions .
 Status –Complete

                                                                                                                                                                                                                                                                                                       

 GROUP 5 COASTAL (2015) N2 Umdloti –Umdloti River Bridge R2 399 630,79.
 Consultants –SMEC Stuart Anderson.
 Contracts Manager –Sean Simmer 071 413 5515.
 Bridge Rehab.
 Status –Complete.

                                                                                                                                                                                                                                                                                             

 WBHO/ROADSPAN ( Feb 2015 to March 2016 ) N3 Upgrade of Section 34- Cedara to Townhill.
 Contact Value R22 326 506,88.
 Consultants Gibb.
 Client – SANRAL.
 Contracts Manager –Thomas Visagie 082 370 8906.
 Concrete Rehabilitation: CRCP & Full Depth Repairs.
 Structural Repairs to Chatterton Bridge.
 Saw cut and Joint Sealing.
 Crack Repairs.
 Status –Complete.

                                                                                                                                                                                                                                                                                                               

 ESOR CONSTRUCTION (2015) –Mbazambo Pipe Bridge.
 Contract Value R2 050 356,64.
 Contract Manager – Peter Elliot.
 Construction of Pipe River Bridge.
 Status – Complete.

                                                                                                                                                                                                                                                                                                           

 FIKILE CONSTRUCTION (2015)–Mooi Mngeni Transfer System.
 Contract Value R154 000,00.
 Contracts Manager – Gary Coetzee.
 Site Agent – Jaco Bekker.
 Various concrete repairs.
 Status – Complete.

                                                                                                                                                                                                                                                                                                         

 FIKILE CONSTRCUTION (Sept 2015 to March 2016) – The Madison ,Umhlanga Ridge.
 Contract Value R291 773,21
 Contracts Manager – Gary Coetzee.
 Site Agent – Rickus Kruger 076 822 6844.

                                                                                                                                                                                                                                                                                               

FAIRBROTHER GEOTECHNICAL (Aug 2015 to Feb 2016) – Rehabilitation Slope on N3 (Van Reenen & Balgowan).
 Contract Value R2 655 411,94.
 Contracts Manager – Eyal Hermelin 076 212 6081.
 Client – N3Tc Douglas Judd.

 Various Ad hock Concrete Repairs to Columns and Beams and Decks.
 Status – Complete.
 Traffic Accommodation.
 Various Bulk Earthworks, Construction of Inlet and Outlet Structures & Grouted Stone Pitching.
 Status – Complete.

                                                                                                                                                                                                                                                                                                         

 TEKWINI CIVILS CC (Nov ’15) – Scottburgh.
 Contract Value R162 130,80.
 Site Agent – Nick Singh 082 360 3070
 Various Diamond Coring to Structures.
 Status – Complete.

                                                                                                                                                                                                                                                                                                     

 LAFARGE -Ridgeview Quarry (Dec 2015 to Jan 2016).
 Contract Value R794 534,49 (*Ready-mix Concrete Supplied by Client).
 Quarry Manager -Theo Pretorius 083 656 8622.
 Earthworks, Constructions of Concrete Slabs & Plinths for new conveyor system.
 Status – Complete.

                                                                                                                                                                                                                                                                                                       

   GROUP 5 COASTAL/PANDEV JV (Dec ‘15 to Aug’16).
 Contract IRPTN Package 4.
 Contract Value R194 252,55 (Final Account).
 Site Agent – Nigel Johnstone 083 988 8460.
 Saw Cutting of various asphalt surfaces.
 Status – Complete.

                                                                                                                                                                                                                                                                                                     

   POWER CONSTRUCTION(September 2016) Kumatsu’s new premises in Meadovale.
 Contract Value R13 296, 60 (Final Account).
 Contracts Manager –Deon McKinley 082 469 3531
 Joint Sealing to Underpass Bridge.
 Status – Complete.

                                                                                                                                                                                                                                                                                                         

   NYONI PROJECTS ( July 2016 to March 2016) Realignment of Rout 2,section 27 at Umhlali & Umvoti River Bridges .
 Contract Value R16 619 381,70.
 Contract No. NRA N002-270-2012/1.
 Contracts Manager – Mclaud Nyoni 082 451 4596.
 Consultants – Naidu Consulting Lothar Worthmann.
 Construction of UCP Concrete Pavements +-21 252m2.
 Construction of in-situ Headwall and various inlet and outlet structures.
 Status – Nyoni Projects in Business Rescue.

                                                                                                                                                                                                                                                                                                         

   WBHO /ROADSPAN (15 Nov’16 to 15 March’16) –NRA 001 The Periodic Maintenance of Route 1,Section 18 Between Koppies and Vaal Toll Plaza.
 Contract Value + -R1 604 409,21 (Final Account).
 Contract No.NRA001-180-2015/1.
 Contracts Manager – Melt Neetling 082 457 1682.
 Site Agent – Thomas Visagie 082 370 8906.
 Consultants – KBK Engineers Isak Joubert.
 Construction of V Drains, Gabions and Repairs to Concrete Pavement at the Vaal Plaza.
 Status – Complete.

                                                                                                                                                                                                                                                                                                                 

 RODS CONSTRCUTION ( 1 March’17 to 31 August’17) –Upgrade and Refurbishment of Toll Plazas on National Route 2,between section 26 and section 28( Mandeni and Dokodweni Toll Plaza).
 Contract Value +- R6 430 133,52.
 Contract No. NRA N002-268-2014/1.
 Site Agent – Len Kassie 083 256 3631.
 Consultants –TBA.
 Construction of CRCP Concrete Pavements +- 9 000 m2.
 Status – Complete.

                                                                                                                                                                                                                                                                                                             

 MURRAY AND ROBERTS (5 Dec’16 to 10Feb’17) – N4 PIENAARS RIVIER TO BELA BELA.
 Contact Value R2 778 161,04,00 (Final Account).
 Contacts Manager -Tommie 083 644 2276.
 Site Agent – Gcina Themba 071 350 3116.
 Saw cutting of asphalt surface 120mm +- 35 838,00meters.
 Status – Complete.

                                                                                                                                                                                                                                                                                             

 WBHO/ROADPSPAN (March 2017) –N3 Upgrade of Section 34: CEDARA TO TOWNHILL.
 Contract Value R297 967, 50 (Final Account).
 Contracts Manager – Melt Neethling 082 457 1682.
 Site Agent – Thomas Visagie 082 370 8906.
 Saw cutting of asphalt slots for drainage +- 6 375,00meters.
 Status – Complete.

                                                                                                                                                                                                                                                                                                       

 GROUP FIVE/PANDEV JV (April’17 to June’17)–IRPTN KWADAKEKA
 Contact Value R136 475,50 (Final Account).
 Contracts Manager –Bradley Naidoo.
 Site Agent – Sean Simmer 071 413 5515.
 Joint sealing to V Drains, Canals and Walls.
 Status – Complete.

                                                                                                                                                                                                                                                                                                           

KINGSWAY CIVILS (May 2017) – IMPALA PLATINUM MINE AT MARIKANA.
 Contract Value R74 350,80 (Final Account).
 Contracts Manager –Rashaad 072 521 9654.
 Diamond coring/Core Drilling of 128no.x 160mm x 50mm holes.
 Status – Complete.

                                                                                                                                                                                                                                                                                                   

 CONCOR ( Nov’17 to Feb’18 –GRAYSTONE PEDESTRIAN BRIDGE,SANTON
 Contract Value R2 000 000,00
 Contracts Manager Pierre Jansen Van Vuuren 083 646 3004
 Joint Sealing ,Spall Repairs ,Soffit Repairs ,Grouting ,Waterproofing etc.
 Status – Complete.

                                                                                                                                                                                                                                                                                                       

   ROADTECH (June 2018) –TURFONTEIN CULVERTS
 Contract Value R1 076 000,00
 Contracts Manager Deon Mackinley 082 469 3531
 Rehabilitation of existing culverts.
 Status – Complete.

                                                                                                                                                                                                                                                                                                 

 CONCOR INFRASTRUCTURE (Sept’18 to Feb’19) –EXXARO BELFAST MINE
 Contract Value –R9 852 000,00
 Contracts Manager Pierre Jansen Van Vuuren 083 646 3004
 Culverts , storm water , V Drains ,Joint Sealing ,Gabions etc.
 Saw Cutting ,jointsealing
 Grouting
 Status – In Progress.

                                                                                                                                                                                                                                                                                                         

 WBHO (Feb’19 to Mch’19 ) EXXARO BELFAST MINE
 Contract Value –R1 000 000,00
 Contracts Manager Fred Sonnendecker
 Saw Cutting, joint sealing.
 Hypolon Bandage
 Status – Complete.

                                                                                                                                                                                                                                                                                               

   CONCOR INFRATRUCTURE (Feb’19) –DRIEFONTEIN WWTW
 Contract Value R36 526,44
 Site Agent Ollie Aadnesgaard 078 801 2589
 Concrete repairs using Epidermix 396 epoxy.
 Status –Complete.

                                                                                                                                                                                                                                                                                                     

   ROAD TECH (April’20 to Aug’20) -MIA BOULEVARD
 Contract Value R1 296 496,90
 Contract Manager Deon Mackinlay
 Waterproofing + Joint Sealing + Cast in situ concrete + Concrete repairs
 Status = Complete.

                                                                                                                                                                                                                                                                                                           

 RAUBEX KZN (June’20 to Feb’21) – N2 Realignment
 Contract Value R20 319 741,00
 Contract Manager Carlo Olivier
 UCP Concrete Pavement + Bridge Rehabs
 Status = Complete.

                                                                                                                                                                                                                                                                                               

   CONCOR INFRASTRUCTURE (Nov’21 to April’22) @ KENDAL POWER STATION
 Contract Value R15 000 000,00
 Contract Manager Pierre Jansen Van Vuuren
 Saw Cutting and Joint sealing
 Status In progress.

                                                                                                                                                                                                                                                                                                       

 BALWIN PROPERTIES (July ’22 to October ’22) @ Munyaka Lifestyle Centre
 Contract Value R3 000 000,00
 Contract Manager Juan Mulders
 Repairs and finishing of all exposed concrete to F1 finish 5000m2.
 Status in progress.

                                                                                                                                                                                                                                                                                                   

 Regards.

 F P Boraine